Improvements to Kings Highway (CR-551S) from Market Street (CR-634) to Hopkins Road (CR-647)

Kings Highway Traffic Control notice

Please be advised that on Wednesday, June 18, 2025 the following work is planned:

  • Segment 1 (Market St. to Rt. 168) is now open and paved, and will have traffic markings installed starting today. Electrical equipment will be installed at Market St.
  • Segment 3 (Hillside Ave. to West Atlantic Ave.) will have a full shutdown to perform drainage crossing work just before the White Horse Pike.
  • Segment 4 (West Atlantic Ave. to Hopkins Rd.) will be pouring curbs & sidewalks in a closed work zone.

Due to the nature of the work and limited roadway width, this closure will need to be in place 24/7 until work is completed. In discussing with the contractor, work is anticipated to take four (4) weeks. Access for residents, emergency vehicles, St. Rose School, and local traffic will be maintained at all times.

If you have any questions or need any further information, please contact Kyle Ebersole, Camden County Assistant Engineer, 856-566-2968 or Paul Nolan, Colliers Engineering, 732-704-5931. We apologize for any inconvenience this work may cause and appreciate your patience and understanding.

Thank you for your cooperation.

Project Information

Name of Project:  Improvements to Kings Highway (CR-551S) from Market Street (CR-634, MP 1.23) to Hopkins Road (CR-647, MP 3.65) Boroughs of Mount Ephraim, Audubon, and Haddon Heights, Camden County, NJ

Start Date: Tentatively, Monday, September 16, 2024

Contract Time: Substantial completion = 340 calendar days

Final completion = 380 calendar days

Limits: Kings Highway (CR-551S) from Market Street (CR-634, MP 1.23) to Hopkins Road (CR-647, MP 3.65) Boroughs of Mount Ephraim, Audubon, and Haddon Heights, Camden County, NJ

A summary of the accelerated schedule is below:

  • 11/18-11/21: 10-hour shifts, 7 am – 5 pm
  • 11/22: Standard 8-hour shift, 7 am – 3 pm
  • Saturday 11/23: Extra 8-hour shift, 7 am – 3 pm
  • 11/25-11/27: 10-hour shifts, 7 am – 5 pm
  • 11/28-11/29: No work
  • 12/2-12/6: 10-hour shifts, 7 am – 5 pm
  • 12/9-12/13: Tentative Standard 8-hour shift, 7 am – 3 pm (based on previous progress)
  • 12/16-12/20: Tentative Standard 8-hour shift, 7 am – 3 pm (based on previous progress)
  • 12/23: Modify traffic control based upon extent of paving in Segment 3
  • 12/24-1/4: Holiday shut down

Project Highlights:

  •  Milling and/or removal of existing concrete pavement and installation of hot-mix asphalt pavement
  • Resurfacing from Market Street (CR-634) to Hillside Avenue (CR-661)
  • Full-depth reconstruction from Hillside Avenue (CR-661) to West Atlantic Avenue (CR-727)
  •  Resurfacing from West Atlantic Avenue (CR-727) to Hopkins Road
  •  Improvements and rehabilitation to existing storm sewer system
  •  Cleaning and lining of existing sanitary sewer system and lateral replacement
  •  Concrete vertical curb, sidewalk, and ADA-accessible curb ramps
  •  Traffic striping, signage, and raised pavement markers

Total Estimated Cost: $10,745,085.83

Contractor: South State, Inc.

Questions? Contact:
Paul Nolan, Project Manager, Colliers Engineering & Design, (732) 704-5931
James Winckowski, Camden County Engineer, (856) 382-2699
Kyle Ebersole, Assistant Camden County Engineer, (856) 566-2968

Project Segments

Market St. to Rt. 168

Progress15%

Rt. 168 to Hillside Ave.

Progress95%

Hillside Ave. to West Atlantic Ave.

STG 1 Progress80%
STG 2 Progress40%

West Atlantic Ave. to Hopkins Rd.

Progress15%

Bi-Weekly Progress Reports

Work Schedule

WeekActivityLocations
6/9-6/13Mill & pave 2″Segment 1, Market St to Rt 168
6/13-6/17Final striping & markingsSegment 1, Market St to Rt 168
6/13-6/20Curbs, sidewalks, and drivewaysSegment 3, Hillside Ave to West Atlantic Ave
6/16-6/17Storm sewer workSegment 3, Hillside Ave to West Atlantic Ave
6/18Sanitary sewer workSegment 3, Hillside Ave to West Atlantic Ave
6/9-6/10Manholes at Amherst & LippincottSegment 4, West Atlantic Ave to Hopkins Rd
6/12-6/13Sanitary sewer laterals, Lippincott to HopkinsSegment 4, West Atlantic Ave to Hopkins Rd
6/9-6/12Concrete curbs, sidewalks, and drivewaysSegment 4, 3rd Ave to 1st Ave

Traffic Control

Please be advised that Kings Highway (CR-551S) at the intersection with Market Street (CR 634) will undergo curb, sidewalk and driveway improvements in Mount Ephraim starting on Monday, March 10, 2025 weather permitting. This work can be done with shoulder closures and lane shifts, and should not have an impact on normal two-way traffic. Working hours will be 7:00 AM to 5:00 PM.

If you have any questions or need any further information, please contact Kyle Ebersole, Camden County Assistant Engineer, 856-566-2968 or Paul Nolan, Colliers Engineering, 732-704-5931. We apologize for any inconvenience this work may cause and appreciate your patience and understanding.

Join Our Mailing List

Enter your email below to be notified of project news, events, and important updates.